| |
| |
Introduction | |
| |
| |
| |
Background | |
| |
| |
| |
The Purpose of the Book | |
| |
| |
| |
Developments and the Direction of Change in the Industry | |
| |
| |
| |
The Three Interlocking Elements of Contracting | |
| |
| |
Chart Demonstrating the Thought Process to be Followed by the Site Team | |
| |
| |
| |
The Tender | |
| |
| |
| |
Introduction | |
| |
| |
| |
Five Column Estimating | |
| |
| |
| |
The Operations Performed by the Estimating Team Prior to Pricing | |
| |
| |
| |
The Pricing Operation | |
| |
| |
| |
The Tender Review | |
| |
| |
| |
Starting Up a Project | |
| |
| |
| |
Introduction | |
| |
| |
| |
The Tender | |
| |
| |
| |
Establish and Brief the Design Team | |
| |
| |
| |
The Contract Programme | |
| |
| |
| |
Subcontractors | |
| |
| |
| |
Submission of Information Requests | |
| |
| |
| |
Establish the Budget | |
| |
| |
| |
Submission of Temporary Works Designs and Method Statements | |
| |
| |
| |
Allocate and Brief Staff | |
| |
| |
| |
Mobilise Plant and Labour Force | |
| |
| |
| |
Dispatch Form F10 to the Health & Safety Executive | |
| |
| |
| |
Conclusions | |
| |
| |
| |
Cost Control | |
| |
| |
| |
Introduction | |
| |
| |
| |
Control of Resources | |
| |
| |
| |
Programming and Planning | |
| |
| |
| |
Benefit of Computer Programming | |
| |
| |
| |
Managing Change with Revised Programmes | |
| |
| |
| |
Setting Direct Resources to Work with Relevant Production Targets | |
| |
| |
| |
Directing Subcontractors | |
| |
| |
| |
Resource Records | |
| |
| |
| |
Financial Control | |
| |
| |
| |
Forecasting of Cash Flow and Contract Outcome | |
| |
| |
| |
Management of Change in Forecasting | |
| |
| |
| |
Maximisation of Receipts | |
| |
| |
| |
Control of Payments | |
| |
| |
| |
The Management of Subcontracts | |
| |
| |
| |
Introduction | |
| |
| |
| |
Nominated Subcontractors | |
| |
| |
| |
Letting a Subcontract | |
| |
| |
| |
The Provisions of the Standard Forms of Subcontract | |
| |
| |
| |
Principal Contractual Administrative Actions Required of the Main Contractor's Project Manager | |
| |
| |
| |
Principal Contractual Administrative Actions Required of the Subcontractor's Project Manager | |
| |
| |
| |
Management of Major Subcontractors | |
| |
| |
| |
Labour Only Subcontractors | |
| |
| |
| |
Management of Labour | |
| |
| |
| |
Introduction | |
| |
| |
| |
The Choice and Composition of a Labour Force | |
| |
| |
| |
The Working Rule Agreement | |
| |
| |
| |
Large Directly Employed Labour Forces | |
| |
| |
| |
Medium Sites | |
| |
| |
| |
Bonus Schemes | |
| |
| |
| |
Typical Industrial Disruptive Tactics and Counter Measures | |
| |
| |
| |
Insurance | |
| |
| |
| |
Introduction | |
| |
| |
| |
Contractor's All Risk Policies | |
| |
| |
| |
Professional Indemnity | |
| |
| |
| |
Action Guidance | |
| |
| |
| |
Contract | |
| |
| |
| |
Introduction | |
| |
| |
| |
Formation of a Contract | |
| |
| |
| |
Key Commercial Actions During the Contract | |
| |
| |
| |
Confirmation of Instructions | |
| |
| |
| |
Notices | |
| |
| |
| |
Records | |
| |
| |
| |
Measurement of the Work | |
| |
| |
| |
Claims | |
| |
| |
| |
Introduction | |
| |
| |
| |
Claim Categories | |
| |
| |
| |
Measurement Claims | |
| |
| |
| |
Claims Under the Contract | |
| |
| |
| |
Global Claims | |
| |
| |
| |
Set off and Claims against Subcontractors | |
| |
| |
| |
Claims Outside the Contract | |
| |
| |
| |
Contractual Principles Applicable to Most Claims | |
| |
| |
| |
Format, Presentation and Content of Claims | |
| |
| |
| |
Descriptive | |
| |
| |
| |
Quantification | |
| |
| |
| |
Negotiation of Claims | |
| |
| |
| |
Adjudication | |
| |
| |
| |
Introduction | |
| |
| |
| |
The Right to Adjudicate and Limitations | |
| |
| |
| |
Actions for a Claimant | |
| |
| |
| |
Actions for a Defendant | |
| |
| |
| |
The Adjudication Process | |
| |
| |
| |
Challenges to an Adjudicator's Decision | |
| |
| |
| |
Design Management and the CDM Regulations | |
| |
| |
| |
Introduction | |
| |
| |
| |
The CDM Regulations | |
| |
| |
| |
Introduction | |
| |
| |
| |
Health and Safety Plan | |
| |
| |
| |
Health and Safety File | |
| |
| |
| |
The Duties and Required Competences of the Entities | |
| |
| |
| |
The Client | |
| |
| |
| |
Planning Supervisor | |
| |
| |
| |
Designers | |
| |
| |
| |
Principal Contractor and Other Contractors | |
| |
| |
| |
Commerical Design Co-ordination | |
| |
| |
| |
Introduction | |
| |
| |
| |
Computer Aids to Design Control | |
| |
| |
| |
Quality, Environmental and Safety Management | |
| |
| |
| |
Introduction | |
| |
| |
| |
An Overview | |
| |
| |
| |
ISO 9000 Quality Systems | |
| |
| |
| |
ISO 14001 and Environmental Management Systems | |
| |
| |
| |
Health and Safety Management | |
| |
| |
| |
Integrated Management Systems | |
| |
| |
Costs Appendix | |
| |
| |
Debugging the Costs | |
| |
| |
The Value in the Company Accounts | |
| |
| |
Subcontract Appendix | |
| |
| |
Checklist for Choice of Subcontractors | |
| |
| |
Checklist for Enquiries | |
| |
| |
Analysis of the CECA Blue Form of Subcontract | |
| |
| |
The New Engineering Contract Subcontract | |
| |
| |
Labour Appendix | |
| |
| |
Typical Incentive Scheme Preamble | |
| |
| |
Typical Problems in Operating a Bonus Scheme on Large Sites | |
| |
| |
| |
Off booking of hours | |
| |
| |
| |
On to loss making targets | |
| |
| |
| |
On to non-productive time | |
| |
| |
| |
Pressure for additional targets | |
| |
| |
| |
Pro Rata | |
| |
| |
| |
Relationship Between Trades' and Labourers' Bonus | |
| |
| |
Disciplinary Code | |
| |
| |
Claims Appendix | |
| |
| |
Rerating Examples | |
| |
| |
Restitutionary Claims | |
| |
| |
Breach of Implied Terms | |
| |
| |
Claims under Tort | |
| |
| |
Ex Gratia Claims | |
| |
| |
Global Claims | |
| |
| |
Contract Appendix | |
| |
| |
Introduction | |
| |
| |
How to Use the Analysis and Contents | |
| |
| |
The Comparison of the Contracts by Subject | |
| |
| |
Index | |